Architect: Design Collective/Samaha Associates Construction Manager: Dustin Construction
Unique Feature: The Media Center utilizes the old undersized gym space and provides space for computer stations as well as traditional print media and books in an open setting.
Swing Plan: Students relocated to Garrison Elementary until the new school was complete.
Selected Academic Focus: Project-Based Learning
INSPIRE Plan: https://planning.baltimorecity.gov/inspire-plans/pimlico-elementary-middle-school - Learn more about INSPIRE (Investing in Neighborhoods and Schools to Promote Improvement, Revitalization, and Excellence) https://planning.baltimorecity.gov/planning-inspire
Total Number of Local Hires: 85
Past Meeting Presentations:
Construction Update Presentation | Mar 11, 2017 download
Construction Update Presentation | Apr 8, 2017 download
*Note: The budget is inclusive of contingencies, phasing, design, construction, FF+E, utilities, demolition/hazmat abatement, commissioning/LEED, testing & inspection and third-party inspection. Click HERE to see a list of contracts awarded for this project.